PUSCH Throughput Conformance Test got throughput 0 with ue.RC = 'A4-3'

1 visualización (últimos 30 días)
In this example, changed the FRC from A3-2 to A4-3, then Run this script, got 0 throughput for all SNR values,not sure anything others needed to change or not?
UE Configuration
User Equipment (UE) settings are specified in a structure form.
ue.RC = 'A3-2'; % FRC number
BRs,
Scott

Respuesta aceptada

Graham Freeland
Graham Freeland el 6 de Feb. de 2019
Should be good, run it and check the throughput curve trend.

Más respuestas (2)

Graham Freeland
Graham Freeland el 5 de Feb. de 2019
Editada: Graham Freeland el 6 de Feb. de 2019
Hi,
You'll have to move the SNR range of the simulation up since the code rate is now a lot higher, going from 1/3 (A3-2) to 3/4 (A4-3). You'll also need to increase the length of the simulation to get reliable results (the simulation example code is set to a short run to make it practical in the first instance).
  1 comentario
Scott REN
Scott REN el 6 de Feb. de 2019
Thanks for the answer, do we have recommended range of simulation length for different code rate?

Iniciar sesión para comentar.


Graham Freeland
Graham Freeland el 6 de Feb. de 2019
The simulation length will generally depend on the channel doppler. A4-3 is used in reference tests using EPA5 or EVA70 channels. The standard specifes very long simulations for RAN4 tests but 1000-5000 subframes may be sufficient for reasonable convergence.
Graham

Categorías

Más información sobre LTE Toolbox en Help Center y File Exchange.

Productos


Versión

R2018b

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by